Sinewave awarded another 132kV project by Sonnedix

Sonnedix have awarded Sinewave Cowley Complex for delivery through 2024 and 2025.

Cowley Complex, a 90MVA 132/33kV project is due to mobilise in Q2 2024 and energise in Q3 2025. Sinewave’s scope includes:

✅ Contestable and private electrical and civil design
✅ Power system studies
✅ Contestable 132kV compound works
✅ IDNO adopted 90MVA 132/33kV works
✅ 2no 33kV metering circuit breakers
✅ 5kM offsite cable route connecting 3 solar parks
✅ 3no 33kV Customer G99 substations

This is our second project with Sonnedix with Gammaton being awarded in 2023 and already in construction.