Enderby Battery Storage
Maximising the existing grid offer through doubling the on-site capacity of battery storage.
Headlines
The safe excavation through existing infrastructure on a live site, over 33kv cables and existing HV earthing.
Designed, supplied and installed a new earth nest to link phase 2 with preexisting phase 1.
Installation of 9km of AC and DC cabling.
Reenergisation of all PCS units and batteries.
700 terminations across HV and LV.
Dead testing and live testing of the LV cables to NICEIC standards, BS7671 18th edition regulations.
HeadlinesHV cable testing to include Earth resistance testing, Over-sheath tests, VLF testing / DC pressure testing, Cold phasing, Hot phasing.
Fall of Potential testing across the site earthing system
A thoroughly interesting project. The 12 week programme mobilisedquickly, despite scope increases duringthe project - specifically aroundearthing inconsistencies from prior installations - we completed tasks on time per schedule.
James Binion - Sinewave Project Manager